Development of two 132 kV feeders at Khaf substation and construction of 20/132 kV substation in Ihya-e-Sepahan as EPC

Development of two 132 kV feeders at Khaf substation and construction of 20/132 kV substation in Ihya-e-Sepahan as EPC

The design has been specified as EPC by the contractor and has been approved by the employer. Implementation of equipment foundation at Khaf substation: 40% progress Implementation of equipment foundation and control room at the mine site substation: 30% progress

Start date 1403/8/22
End date 1404/11/22
Progress percentage 25 percent
Remaining percentage 75 percent

Main Objective of the Project

Given the power supply of the entire mining site of the company through the existing substations in the area (mines in operation) of Shahr Sangan, Sepahan Iron Ore Mining Company has decided to separate the power transmission line (another contract) and construct completely separate substations at the mining site of the company and has planned to supply power to the concentrate production plants, the central laboratory, HSE, office facilities, and in the future, the buildings under design (office buildings, central industrial kitchen and medical) through a separate line.